Construction of Tunnels between Tampines East and Upper Changi Stations

Client:         
Contract:   
Location:   
Period:    
Land Transport Authority
Build
Tuas, Singapore
2011 - 2016

The Downtown Line Stage 3 C923A project include the construction of tunnels between Tampines East and Upper Changi Stations with a total length of 4.76km, a TBM launching shaft and eight cross passages. Two 6.35m diameter EPB machines were used to construct the bored tunnels.

C923A Awards
2013
LTA ASAC Accident Free Recognition Award