top of page
T316
Underground Infrastructure
Changi Airport
T316
Underground Infrastructure
Changi Airport
Twin bored tunnels from Changi Airport Terminal 5 to Changi Airport (CGA) Station Terminal 2
LTA DTL3 C923A
Construction of Tunnels between Tampines East and Upper Changi Stations
Client:
Contract:
Location:
Period:
Land Transport Authority
Build
Tuas, Singapore
2011 - 2016
1/3
The Downtown Line Stage 3 C923A project include the construction of tunnels between Tampines East and Upper Changi Stations with a total length of 4.76km, a TBM launching shaft and eight cross passages. Two 6.35m diameter EPB machines were used to construct the bored tunnels.
C923A Awards
2013
LTA ASAC Accident Free Recognition Award