Changi Airport
Twin bored tunnels from Changi Airport Terminal 5 to Changi Airport (CGA) Station Terminal 2
LTA DTL2 C920
Construction of underground Newton Station
Client:
Contract:
Location:
Period:
Changi Airport Group
Design and Build
Changi Airport, Singapore
2023 - 2028
1/4
The Downtown Line Stage 2 C920 project is a design and build project include the construction of Newton Station, four tunnels that connect Newton Station to Little India Station and Stevens Station with a total length of 5.32km and a Cable Tunnel using pipe Jacking method. Four 6.35m diameter EPS machines were used to construct the bored tunnels.