top of page

LTA CRL CR203

Design and Construction of Turf City Station and Tunnels for Cross Island Line

Client :
Contract :
Location :
Period :
Land Transport Authority
Design and Build
Turf City, Singapore
May 2024 - Jun 2032
7.24m
Slurry TBM Machine
3,000m
Bored Tunnels

Contract CR203 involves the design and construction of an Underground CD station Turf City Station and a 3km bored tunnel towards CR205 King Albert Part Station.

The tunnel will be constructed with two slurry TBM. The contract also comprises a TBM launch shaft and a new road connecting the Station to Eng Neo Avenue.

Related Projects
T305_Concourse_1_edited_edited.jpg
CR202
Cross Island Line

Design and Construction of Bored Tunnel between Fairways Drive and Sin Ming Walk.

T305_Concourse_1_edited_edited.jpg
CR102
Cross Island Line

Design and construction of 6-km long tunnels between Aviation Park Station and Changi East Depot.

bottom of page