PUB TWRP Contract 1

Tunnel with Twin Water Pipelines from Tuas Water Reclamation Plant to Jurong Island

Client:         
Contract:   
Location:   
Period:    
Public Utilities Board
Design and Build
Tuas, Singapore
2021 - 2024
6m ID
1,600m
Slurry TBM
Undersea Tunnel

PUB TWRP Contract 1 comprises of a construction of 6m internal diameter tunnel from the proposed Tuas Water Reclamation Plant (TWRP) / Tuas NEWater Factory to existing network in Jurong Island, construction of tunnel launching and receiving shafts and the installation of twin 2200mm and 1200mm diameter pipelines within the tunnel, pipelaying by cut and cover method, installation of pipeline appurtenances and construction of associated chambers.

Related Projects
T225_Substantial Completion_edited_edite

Construction of bored tunnels with a total length of 5.8 km for PUB DTSS Phase 1

T-01
Deep Tunnel Sewerage System Phase 1
T305_Concourse_1_edited_edited.jpg

A 6 km South Main Sewerage Tunnel and 5.5 km South Linkway Sewerage Tunnel.

T-11
Deep Tunnel Sewerage System Phase 2
bottom of page