2019 © STECS All Rights Reserved.

Singapore LTA CCL4 C855

Construction of the underground Holland Village Station, Buona Vista Station, Kent Ridge Station and One North Station 
8,250 m Bored Tunnels
6.35m Diameter EPB Machine

Project: The Circle Line Stage 4 C855 project is a design and build project which STECS undertook in the name of a joint venture with Woh Hup and Alpine Mayreder. This project includes construction of Holland Village Station, Buona Vista, Kent Ridge and One North Station, 8.25km TBM tunnels and 0.35km C&C tunnel. Two 6.35m diameter EPB machines and two 6.35m diameter slurry machines were used to construct the bored tunnels. The contract value is S$399.91 million. 

1/3